ITI developed a custom racking system for hydroelectric switchgear, enabling individual feeder maintenance without a full facility shutdown.
LOCATION
British Columbia
MANUFACTURING LEAD TIME
28 weeks from release
INDUSTRY
Hydroelectric Power Generation
SOLUTIONS
PROJECT OVERVIEW
The 13.8 kV, 1,200 A switchgear distributes generator power to utility grid feeders. ITI developed a custom racking system for four withdrawable breakers in an outdoor enclosure. Long lead times for key components added schedule pressure. The team coordinated design updates and accelerated assembly and factory testing to help recover time. Operators can isolate individual feeders for maintenance without shutting down the entire facility. The design also includes provisions for future feeder expansion.